A2 Schedule
October 19:
Finalize initial rules of game and card list. Make initial no-art testing cards.
October 21:
Start sketches for cards, finish 3 card sketches (for style reference)
October 26:
Playtest game over weekend (a few tests, with different groups). Document results of playtest. Sketches for all cards done (unless I determine more are needed after the playtest).
October 28:
Decide on colors and templates for finished cards, work up template.
November 2: (5% Deadline)
Initial card set done (front and back). Rules finalized and copy written up.
November 4:
Decide on revisions to cards that need to be made. Finalize card list.
November 9:
All final cards sketched up. Sketches for box art, game board and rulebook. Initial layout for rulebook.
November 11: (Veteran’s Day)
November 16:
Refinements of box art, game board, rulebook art. Revised rulebook layout. Back of box copy.
November 18: (10% Deadline)
Final cards done. Final rulebook done & assembled. Final front box art done. Full box layout drafted.
November 23:
Full box layout done (including internal structure). Store box planned and variated.
November 25: (Thanksgiving)
November 30: (15% Deadline)
Whole project assembled, ready to present.
December 7: (Final Due)
Refined finals of everything, project turned in.